Capacity of the Plant/Unit (at 100% capacity utilization)
Shed
| Land (own) | 00.00 |
| l works and Buildings (500 sqft @200/sqft) | 1.00 |
| Machinery | 0.63 |
| Others | 0.30 |
| Sub-total (A) | 1.93 |
| Total Working Capital Req (B) | 0.59 |
| Total Project Cost (A+B) | 2.52 |
| Amount | Percentage | |
| TERM LOAN (75% of A) | 1.45 | 57% |
| WORKING CAPITAL (60% of B) | 0.35 | 14% |
| Total Loan | 1.80 | 71% |
| Equity | 0.72 | 29% |
| Total Funds Required | 2.52 | 100% |
Year |
Year |
Year |
Year |
|
|---|---|---|---|---|
| Target Revenue | 13 | 14 | 16 | 18 |
| Break Even Point | 54.20% | 46.49% | 40.00% | 35.09% |
| DSCR including Principal Repayment | 5.21 | 3.63 | 4.77 | 6.13 |
| Production of Bamboo Beer Bottle Holder | 8 semi-skilled labour will make on average 5 semi-finished bamboo bottle holders per day. The skilled labour will do the finishing on the turning machine while the unskilled labour will help in the material handling and packing |
| Machinery T | his is a profile of a household level enterprise with 9 hired labour. |
| Interest rate assumed | 11% |
| Repayment period | 5 Years with 3 months moratorium |
| Training Institutes | CBTC Meghalaya, BCDI Agartala, IIE Guwahati, TRIBAC |
| Whether the service is in the Negative list under NEIDS and MSME? | No |